Project: phowe   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Philip Howe   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1711.75
Total Flight Time:6
Total Expense:N/A
Start/Last Date:Oct 19, 2020 - No Finish Date
Engine:Rotax 915is
Propeller:Whirlwind
Panel:Dynon
 
Friendly URL: https://eaabuilderslog.org?s=phowe

Home or Last Project Picture

Apr 17, 2024     Tighten Rudder Cables - (1.5 hours)       Category: Controls
We went back and forth loosening and tightening the front pully and changing the attachment holes on the various tangs. We finally got the front pully cable, rudder cable, and the rudder return cable tight enough to my satisfaction.


 